Installation of entrance doors in the 4th and 7th floor apartments of the first entrance has been completed. Installation of heating and gas pipes in the 7th and 10th floor apartments of the 2nd entrance has been completed. Internal plastering works are underway in the 17th and 19th floor apartments of the 2nd entrance. Ventilated facade installation works are underway. The installation of the elevator of the second entrance started.